« Selling 15 National Parks For Job Seekers - A site worth looking at ... »

Critical Path in Schedule Management

10/06/05 | by Clarise | Categories: Project Management

Project Management Network Diagrams are helpful in determining where most of the schedule project risks will occur. A critical path is made up of activities that cannot be delayed without delaying the end date of the project.

How does one compute the critical path? The simple example below illustrates the process. If one has a network diagram such as:

Click to view original size

Find all the possible activities and the corresponding duration:

Then, the fun part ... Trace all the possible paths then sum up all the duration.

Click to view original size

From the simple example above, our critical paths are:
Start-A-B-E-F-C-End and Start-D-B-E-F-C-End.

Computing the critical path is a good way to manage project schedules and associated risks. If you are not using it, try it and it may make a big difference for you.

Send feedback »
 

No feedback yet

July 2019
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        
 << <   > >>
This blog contains thoughts that range from non-technical to technical. Its name is derived from "Yakity Blah Blah" a column I once had that discussed a cornucopia of ideas. Who am I? I'm Clarise Z. Doval Santos, providing Project Management and Technical Leadership for data management and analytic, data science, IoT and sensor analytics ecosystems 37.652951177164 -122.490877706959

Search

  XML Feeds

blogging software